1999 to 2000 – Implementation period

Refurbishment of Pirana and SuhaReka Substations, 33/11kV

Turn-key project

Customer: KEK Power Corporation of Kosova

Value: 2 Million EURO

FINANCED BY: IBRD
  • Includes 33kV switchgear
  • Relay protection and control equipment
  • AC and DC Supply
  • Design
  • Erection
  • Testing and commissioning
  • Training etc.