2003 to 2004 – Implementation period

Pre-paid energy meter system

Customer: Electricidade de Timor Leste

Value: 3 Million US Dollar

FINANCED BY: NORAD from Norway
  • 17.000 pre-payment meters
  • Complete central master station
  • Vending stations with selling terminals
  • Installation of meters and vending and master central stations
  • Training courses

2001 to 2003 – Implementation period

Pre-paidenergy meter system – Interim Management of EDTL

Training and Network analyses

Customer: Electricidade de Timor Leste

Value: 2 Million US Dollar

FINANCED BY: NORAD from Norway
  • 10.000 pre-payment meters
  • Complete central master station
  • Vending stations with selling terminals
  • Installation of meters and vending and master central stations
  • Training courses



2001 to 2002 – Implementation period

New power plant. Total capacity 6 MW – Turn-key project

Customer: Electricidade de Timor Leste

Value: 4,5 Million US Dollar

FINANCED BY: NORAD from Norway
  • Four (4 ) units of power modules
  • Step-up transformers for each gen. set
  • 20 kV connection to the existing switchboard
  • Balance of plant mechanical and electrical auxiliary equipment
  • Engine auxiliaries module and engine control panel
  • Design
  • Erection
  • Testing and commissioning